Currently paving & gravelling to front gardens, and installing metal fencing.
brickwork to wall 540 & 518. A few hours lost to rain last month. We are dropping back to complete the late sign ups and do any works variations. No accidents to report since last site meeting. All brickwork to late sign ups should be completed by 2/07/10 and all paving & gravelling to gardens complete by 16/07/10. We are on course to complete as per our programme